Works moving ahead in Gibsons Place

The works that I described in a February post to tackle the flooding problems around Gibsons Place have taken place in two parts. Proceeding to the second stage was very dependent on Kent Highways reaching agreement with the management company for the development, and those works - as shown in the picture - are now well under way.

The first stage of the works was to put a large containment area into the road, with pipes bringing water from the previous, flood-prone gullies and into this storage space. Even on its own, this first phase has had a significant effect, as can be seen from the significant reduction in flooding even in recent periods of heavy rain.

The current phase involves installing further pipework from the High Street to the existing head wall. This is proving to be tricky work, with a lot of utilities to be navigated, and has had a significant impact on residents' access to parts of the development. This should be eased once the works get to the archway towards the back of the development, which (with two crews working on it) should be achieved within a week, weather permitting.



Two pipes will run from the containment area to a catch pit (to remove much of the silt in the water), at which point a single pipe will take the water to discharge into the river. As previously reported, there will be a flap over the end of the pipe to prevent water flowing back into the system when river levels are high.

The works already carried out have had a significant effect, and hopefully the completion of the second stage of the project should see a lasting resolution to this long-standing problem